B - Preparation of Arnside Parish Plan

B.      Preparation of Arnside Parish Plan

[Asterisks indicate documents available, on request, on CD-Rom.]

  • early 2002: discussion of ‘Vital Villages’ documentation at Parish Council
  • expression of intent forwarded
  • enquiry sent to all village organisations and businesses: no opposition, sufficient support to justify pursuing the possibility of a Parish Plan
  • the matter of a Plan raised from the floor at Annual Parish Assembly, April 2002: generally supported
  • Parish Council commits fully to Plan and designates a member to set procedures in motion (May 2002)
  • same member attends Cumbria Voluntary Action/Cumbria Rural Development workshop on Parish Plans (May 2002), and makes initial contact with Rural Community Officer
  • Parish Council agrees (10 June 2002) to: (i) a schedule for applying for funding, preparing and presenting a five-year Plan; (ii) arrangements for beginning to establish a Steering Group and the holding of a first meeting, open to the public; (iii) a financial contribution
  • July 2002: first public meeting - widely advertised - takes place: Chair of Steering Group elected; first members elected to Steering Group. (As anticipated, membership of the Steering Group – which stood mostly at 10-12 – was to change regularly over the twelve-month period, although five or six members remained throughout the whole planning process.)
  • four full meetings of Steering Group, Aug-Oct 2002
  • Parish Plan Open Day, 16 November 2002: around 300 residents attend; some 200 leave written comments*
  • eight further meetings of Steering Group, Nov-Feb 2002-03
  • Feb 2003: circulation of some 1200 copies of a questionnaire to all households in the Parish - questionnaire is 24 pages long, with 73 questions*
  • Feb-March 2003: 599 questionnaires returned, covering 53% of Parish population
  • eight further meetings of Steering Group Feb-June 2003
  • transfer of results of each completed questionnaire onto a one-page grid;*  transfer of results from grids onto a specially-designed database*
  • interrogation of database and transfer of results onto a specially-designed spreadsheet*
  • brief preliminary oral report on results of survey at Annual Parish Assembly, 24 April 2003
  • recruitment and establishment of 5 ‘Task Groups’, corresponding to areas of opinion in the questionnaire results, a 6th area being covered by the Steering Group itself*
  • preliminary printed report on selected results of survey made available to residents (May 2003)*
  • early June 2003: Task Groups report back to Steering Group, which drafts Action Plan
  • Parish Plan ‘Drop-in’ event, 21 June; around 130 residents attending, who
    • are given a new document (with graphics) setting out full numerical results of survey*
    • see a draft Action Plan
    • have a last opportunity to make comments
  • four further meetings of Steering Group July-August 2003, taking account of latest comments and information in revising Action Plan and drafting whole Parish Plan
  • August 2003: Parish Plan completed
  • August 2003: Parish Plan printed
  • Sept 2003: leaflet summarising Plan is devised, printed and circulated to all Arnside households*
  • 1 Oct 2003: public meeting to launch Plan and establish new Parish Plan Management Group to supervise and monitor carrying out of Plan.